2023
- Public community meeting on new building
- Finalize design elements
- Advertise demolition documents
2024
- Advertise and conduct Act 34 hearing
- Submit building plans to PDE
- Finalize demolition of structures
- Advertise and award contract for new building
- Break ground on new building
2025
- Construction on new building continues
- Initiate process to close Elroy and Moore
2026
- Estimated opening of new building
- Sell Elroy and Moore properties
Please note that the above timelines are subject to change. This timeline will be updated throughout the life of the project.